Error 153.x Basin not filled


Description

PRC with level control
In production
In the PRC with level control, the lacquer shell is not filled within the time calculated in the set-up.
In the set-up
In PRC with level control, the lacquer shell in the set-up is not filled within the maximum time (parameter: initial time at switch-on).

Remedy

  • Execute PRC level control setup. 
  • Increase parameter for initial time at switch-on. 
  • Check lacquer flow on the can body. 
  • Check lacquer tank. 
  • Check the lacquer tubes. 
  • Check the lacquer level sensor A015:In6. 
  • Check the digital input